Today, August 2, paver installation was completed in Emanuel Court, and curbing was formed and poured to secure pavers into place. Weather permitting, the sand and polymer will be installed to finalize the paver installation early next week. 

The East entrance into English Plaza Parking is now open for use. However, the Eastern most entrance into White Street lot will remain closed till Monday while concrete cures. The contractor will also be removing debris, construction equipment and vehicles out of English Plaza Parking lot to free up the remaining parking currently inaccessible and or blocked off.

Next week, the contractor will be grading islands and cleaning debris in preparation for the lighting and Landscaping contractors coming in to perform their work.