On August 5, curbing was poured in Emanuel Court. Additionally, the islands in English Plaza were graded in preparation for landscaping over the course of the next two weeks. The entrance to English Plaza from West Front St. and the new entrance to the White Street Lot from are closed. The contractor will be performing major cleanup throughout the entire project area this week. The installation of topsoil into planters will begin on Tuesday, August 6; planting will start Wednesday, August 7 and continue for approximately two weeks. Beginning Thursday, August 8, electrical contractors will be on site over the next two weeks to prepare and install lighting fixtures.