Update: October 3, 2019

The contractor, Seacoast Construction, will be redoing a section of the English Plaza lot between Investors Bank and the row of English Plaza stores (Domino’s Pizza, In Between Café, etc). The work requires milling and re-paving and is scheduled for Monday, October 7, weather permitting. Seacoast Construction expects to complete both Read more…

Update: September 16, 2019

It’s open! The English Plaza parking lot reopened this morning. It’s new layout will improve traffic flow and safety from West Front Street to White Street. While the bulk of the work has been completed, there is still some utility work, landscaping and other punch list items to be completed Read more…

White St base paving layer installation

Update: Sept. 4

White Street is looking better each day! Milling and prep work was completed on Tues., Sept. 3. The base pavement layer was installed today. Weather permitting, final paving will be put down on Sept. 5 & 6. The top coat of pavement requires 48 hours to cure before vehicle traffic Read more…

Update: August 31

Paving for the White Street/English Plaza Streetscape will begin September 3. The work will be done in two phases: each phase is scheduled to take approximately one week. All businesses will be open – Shop local. Please note that all dates and schedules are weather permitting. Week 1: September 3 – Read more…

Update: August 27

On Wednesday, August 28, three bucket trucks will be at the project site and workers will be installing the light canopies, banner arms, and finishing a number of coordinated utility functions. The entrances to English Plaza are expected to remain open with brief closures for the moving of equipment and Read more…

Update: August 26- 30

This week, the contractor will continue to work on punch list items and prepare the project site for paving. Weather permitting, electrical work will be completed. Paving work will begin after Labor Day. Meetings are scheduled with the affected property owners and businesses. The paving schedule will be posted to Read more…

Update: August 19

Weather permitting, the electrician will be onsite all week, pulling wires and installing lighting, meter boxes, and electric meters in English Plaza and in the White Street project area. There are no scheduled traffic changes or closures for the week.

Update: August 12

A work crew from JCP&L was on site to remove a utility pole from English Plaza today. The Contractor installed the polymer mixture on the remaining pavers, and the landscaper was on site to water and check the plant installations. The landscaper and a JCP&L crew will be back on Read more…