Update: August 19

Weather permitting, the electrician will be onsite all week, pulling wires and installing lighting, meter boxes, and electric meters in English Plaza and in the White Street project area. There are no scheduled traffic changes or closures for the week.

Update: August 8

August 8, landscaping  and mulch installation was completed throughout the project area. Bollards were painted and the electrician was on site performing his preliminary work. On August 9, electrical work continues and the contractor will address punch list items throughout Read more…