Update: June 18

On Tuesday, June 18, ADA ramps were placed, and pavers were installed in English Plaza. Tomorrow, 6/19, paver installation continues, and concrete curb will be poured. White Street will be open to vehicles and pedestrians.

update: June 17

On June 17, pavers were placed in English Plaza, concrete curbs were poured and concrete sidewalk was removed. Tomorrow, Tuesday, June 18, paver installation will continue in English Plaza. White Street will be open to vehicles and pedestrians.

Smoothing fresh concrete at the White St. entrance to English Plaza.

Update: June 12

On Wednesday, June 12, concrete foundations for light poles and pay stations were poured, as well as concrete aprons, sidewalks, and ADA ramps on the west side of English Plaza. Thursday, June 13, weather permitting, paver installation is scheduled for Read more…

Update: June 6

Today, drainage work continued, and electrical conduit was placed in English Plaza. Tomorrow, June 7, drainage work and paver installation will continue, and site cleanup will commence. Both lanes of White Street will be open to vehicles. Use these hashtags Read more…

Update: June 5

On Wednesday, June 5 curbs were poured in the White Street lot. Concrete sidewalk in English Plaza was removed for replacement, and stormwater pipes were placed. Tomorrow, June 6, stormwater drainage work continues. Both lanes of White Street will be Read more…

Update: June 4

On June 4, new curbs were poured in the White Street lot, and stormwater pipes were placed. Tomorrow, June 5, stormwater drainage work will continue. White Street will be open to vehicle traffic. The street will be closed to vehicles Read more…

Update: June 3

Demolition began in the White Street lot today. Existing curb and sidewalk were removed, and curb forms were placed. Tomorrow, June 4, new curbs will be poured. Both lanes of White Street will be open. #whitestreet #englishplaza #redbanknj