Update: August 8

August 8, landscaping ¬†and mulch installation was completed throughout the project area. Bollards were painted and the electrician was on site performing his preliminary work. On August 9, electrical work continues and the contractor will address punch list items throughout Read more…

Update: August 7

Today, August 7, landscapers continued the installation of bushes, grasses, and flowering plants and began planting trees throughout EnglishPlaza.  Tomorrow, August 8, weather depending, the electrician is expected to begin running wires for outdoor fixtures.

Update: August 6

On August 6, landscapers arrived on site with plants and top soil.  Bushes, grasses, and flowering plants were installed, and preparations were made for the arrival of trees tomorrow.  All vehicular entrances are open and should remain open until paving Read more…

Update: August 2

Today, August 2, paver installation was completed in Emanuel Court, and curbing was formed and poured to secure pavers into place. Weather permitting, the sand and polymer will be installed to finalize the paver installation early next week.  The East Read more…

Update: August 1

Today, brick pavers were installed in Emanuel Court. Tomorrow, August 2, brick paver placement continues in Emanuel Court, and the Contractor, Sea Coast Construction, will begin clearing site to allow for more public parking. The alley portion of Emanuel Court Read more…

Update: July 30

On Tuesday, July 30, work in English Plaza continued with concrete sidewalk and curbing being poured, along with paver placement. On July 31, the placement of pavers will continue in English Plaza. Additionally, vehicles will need to enter English Plaza Read more…